Sept. 19 –

  • Paving has been completed. The road will be fully opened by Friday, September 21, 2018.
  • Streetlight bases and lights scheduled to be installed next week.
  • There will be intermittent lane/parking restrictions as the remaining concrete and landscaping is finished.
  • Tentative completion date is September 27, 2018.

June 6 – Road closure on Macleod Trail S.W. between 8 St. S.W. and Diebert Close

May 14 – Temporary tree removals required for Southwest Main Replacements (Phase 3 finishing work)

Summary:

This project involves the replacement of flood damaged underground sanitary sewer and water infrastructure. As part of the work, the roads will also be rehabilitated.

 

Location:

This project will be undertaken on Macleod Trail from 7th Street SW to Highwood Trail. It also includes installation of a new water main on 9th Ave SW between 8th St SW and 9th St SW.

 

Timing:

This project is scheduled to begin the spring/summer of 2018 and be completed by fall 2018.